Streetcar comeback … makes a comeback!


Cincinnati streetcar, provided by CAF, under live power testing in 2015. Photo via Dilemma-X.

Cincinnati streetcar, provided by CAF, under live power testing in 2015. Photo via Dilemma-X.

For a while, eager naysayers and rail transit critics said the return of streetcars to American streets — the modern-day streetcar renaissance — was over. They brandished problems with various streetcar projects, including the political cancellation of a line in Arlington, Virginia, missteps with Washington, DC’s new streetcar project, troubles with rolling stock procurements in Oklahoma City, and political cancellation of the planned streetcar starter line in Providence, Rhode Island.

But out of the gloom, new streetcar projects are succeeding, with more on the way. Those vehicle procurement problems have been resolved, and Oklahoma City’s project continues to proceed. Here’s a list of what seem to be currently the major projects in the mix:

Seattle — First Hill Streetcar, an expansion of the original streetcar system that began with the South Lake Union line, opened January 23rd. The 2.5-mile-long project was installed at a cost of $134 million.

New Orleans — The Regional Transportation Authority’s 1.6-mile North Ramparts-St. Claude Streetcar Line Project, budgeted at $40-41 million, is nearing completion, with opening expected this summer or early fall.

El Paso — The city’s 4.8-mile heritage streetcar line project, budgeted at $97 million, is now under way, with the legacy fleet of stored historic PCC cars now being renovated and restored by Brookville Equipment Corp.

Oklahoma City — A 4.6-mile, $129-million streetcar starter line project continues to proceed, with rolling stock supplier designated as Brookville Equipment Corp.

Milwaukee — The city’s 2.1-mile, $124-million downtown streetcar starter line project is now well under way.

Detroit — The 3.3-mile, $140-million M-1 streetcar project, mainly routed on the city’s iconic Woodward Avenue, continues to move ahead.

Kansas City — The 2.2-mile-long, $102-million project is nearing completion, and expected to open in a few months.

Cincinnati — The city’s 1.8-mile, $148-million core area streetcar project (see photo at top of post) is nearing completion, and expected to open this fall.

Washington, DC — Officials are now hoping the problem-plagued, long-delayed 2.2-mile H St.-Benning Rd. streetcar project, costing approximately $200 million so far, will at last be completed and able to open within a few weeks.

Tucson — The city’s 3.9-mile Sun Link streetcar starter line, opened in 2014 at an investment cost of about $199 million, continues to exceed its ridership projections.

Atlanta — The 2.7-mile-long Peachtree district streetcar starter line, completed at a budget of $93 million, also opened in 2014. ■

Kansas City streetcar procurement “piggybacks” on Cincinnati’s CAF order


CAF Urbos 3 streetcar for Kansas City. Graphic: CAF.

CAF Urbos 3 streetcar for Kansas City. Simulation: CAF.

Kansas City — By “piggybacking” its order for streetcar rolling stock on Cincinnati’s order, Kansas City has probably saved at least several million dollars in the cost of its streetcar project.

This past October, Kansas City took advantage of the “piggybacking” opportunity and awarded a $22 million contract to CAF USA, a subsidiary of Spain’s Construcciones y Auxiliar de Ferrocarriles S.A., for five streetcars to provide service over its 2.2-mile downtown streetcar starter line, now under construction. (For background, see Kansas City — Another new downtown streetcar project starts to take shape.)

The Urbos 3 streetcars, costing a relatively bargain price of roughly $4.4 million each, will be assembled at CAF’s plant in Elmira, N.Y. The order follows (and is linked to) CAF USA’s contract with Cincinnati, which also involves five streetcars. (Thanks to Railway Age for details.)

Via a Twitter message link from John Schneider, here’s a look at CAF’s Urbos 3 streetcar running in Spain:


Hopefully, within a few years we’ll see a very similar model running on the streets of Cincinnati and Kansas City.

Kansas City — Another new downtown streetcar project starts to take shape


urt_kc-lrt-stc-sim-sb-Main-19th-St-2012x_Dntn-Corr-AA
Simulation of streetcar southbound on Main St. at 19th St. [Graphic: Downtown Corridor Alternatives Analysis]

Kansas City, Missouri — At a March 6th public meeting, city planners presented details of their construction schedule for Kansas City’s proposed 2.2-mile, $102 million streetcar project, approved by voters in late December (2012). The details may be instructive for streetcar advocates in other cities, giving them an idea of what’s typically involved in this kind of project.

The line is planned to run through the city’s Central Business District from River Market to Union Station, also serving Crossroads and Crown Center. According to a Dec. 28th report in the Kansas City Business Journal, “Proponents of the plan say the line … will spur development along Main Street while helping to attract young, creative residents to the city’s urban core.” The system is currently projected to open for service in 2015.

urt_kc-lrt-stc-map-proposed-2012_Dntn-Nbhd-Assn-KC
[Map: Downtown Neighborhood Association of Kansas City]

Particularly for transit supporters in other cities considering a streetcar or large light rail transit (LRT) system, it’s instructive to look at the elements of this kind of project. A more recent report (March 7th) in the KC Business Journal provides an opportunity for this kind of examination, laying out the three main phases of the project.

At more than $46 million a mile, KC’s streetcar line will be far less costly than, say, a subway or monorail, or even many busways — but that per-mile price tag also buys a lot more than just the rail transit infrastructure, as we’ll see. First, let’s itemize the railway components themselves, some of which will occur over several of the phases:

• Streetcar rolling stock — to be selected, ordered, delivered.
• Tracks installation along Main Street from the River Market to Union Station.
• Rolling stock maintenance facility in the River Market to be designed.
• Underground utilities to be relocated.

That last item — relocating utilities — is not directly part of the rail infrastructure, but it’s a task that usually has to be done (although there are some ways to minimize or avoid it). In many cases, the utilities may have actually needed replacement for years, but the municipality or private utility owner holds off, hoping that the rail project will pick up the tab. There’s also wide divergence from city to city in terms of who the law specifies should be responsible for paying for such relocation — the agency sponsoring the rail project, or the utility owners.

Phase 1 (from 2013 until early 2014) will mainly focus on utility relocation and the construction of the maintenance facility. Utilities work will include:

• Opening trenches to remove and relocate utility lines.
• Suspending temporary overhead lines for temporary utility relocations.

According to the news report, this work will be done in three-block sections and taking two to eight weeks. “During the work, Kansas City residents can expect partial lane closings and temporary service interruptions.”

Work on the maintenance facility, lasting 12 to 18 months, will include:

• Clearing the site for the facility and starting construction of the building’s foundation.
• Commencing civil engineering work startup of actual shop construction.

Phase 2 (from late 2013 to late 2014) includes track installation (in pavement), station construction, and rebullding of streets and sidewalks. It’s debatable whether this last item, street and sidewalk reconstruction — routine for most urban rail projects — should be considered an indispensable component of the rail transit and assigned as a cost totally to the rail project.

To some extent, as with utilities, public works planners often realize that the streets and sidewalks need to be rebuilt anyway, and often wait to let the cost be picked up by the rail project. Also, these kinds of upgrades might be considered as more in the category of “urban amenities”, and some rail advocates argue they should be tallied separately as something like “urban renovation”.

On the other hand, it’s arguable that effective access to the new line requires good pedestrian facilities. Furthermore, for federal funding the Federal Transit Administration usually requires it (along with other amenities not directly essential to the transit operation, such as artwork at the stations).

In any case, both for track installation and the street/sidewalk reconstruction, the project schedule calls for closing “two city blocks … for three to four weeks to accommodate construction of the streetcar’s tracks and stops.” This will include:

• Removing existing pavement and sidewalks.
• Reconstructing sidewalks, curbs, and gutters.
• Installing railway hardware on track slabs with drainage facilities and special trackwork (switches, crossovers, etc.).
• Rebuilding existing curbs, gutters, and sidewalks near stations.
• Building concrete platforms and canopy foundations, and installing “amenities and finishes at the streetcar stops.”

As the Business Journal report indicates,

Construction of each station is expected to last three to four weeks. Track installation will require a 20- to 25-foot work zone and will close multiple lanes or entire sections of Main Street, depending on the width of the street at the work location.

Phase 3 (from late 2013 to late 2014), the final phase of construction, will focus mainly on the power system and traffic signals, with some replacement of street lighting (again, this last item may be one of those “urban amenity/renovation” elements not strictly essential to the urban rail project). There’s an advisory that “Temporary closures during non-peak hours are expected at each two-block section for the three to four weeks it will take to complete this phase of the work.” This last phase will include:

• Installing the overhead contact system (OCS) — i.e., the support poles and wiring for the electric propulsion system (this is often erroneously referred to as “catenary”, which is actually a somewhat heftier type of OCS; however, many streetcar lines and even some larger LRT lines use much simpler single-contact-wire OCS to minimize its visibility).
• Installing new traffic signals and street lighting (again, see the discussion above about “urban renovation” and whether the cost of these project elements should be assigned to the urban rail project).
• Installing power substations (these are just relatively small power booster units to maintain adequate voltage on the OCS, which tends to drop because of the resistance of the OCS wire).

“After construction is complete,” notes the Business Journal report, “the city expects to take four to six months for testing and startup work between late 2014 and early 2015.”

That, then, is what this relatively small KC urban rail project will involve. Hopefully, this information will be helpful to those of you contemplating similar projects for your own cities.