Streetcar comeback … makes a comeback!


Cincinnati streetcar, provided by CAF, under live power testing in 2015. Photo via Dilemma-X.

Cincinnati streetcar, provided by CAF, under live power testing in 2015. Photo via Dilemma-X.

For a while, eager naysayers and rail transit critics said the return of streetcars to American streets — the modern-day streetcar renaissance — was over. They brandished problems with various streetcar projects, including the political cancellation of a line in Arlington, Virginia, missteps with Washington, DC’s new streetcar project, troubles with rolling stock procurements in Oklahoma City, and political cancellation of the planned streetcar starter line in Providence, Rhode Island.

But out of the gloom, new streetcar projects are succeeding, with more on the way. Those vehicle procurement problems have been resolved, and Oklahoma City’s project continues to proceed. Here’s a list of what seem to be currently the major projects in the mix:

Seattle — First Hill Streetcar, an expansion of the original streetcar system that began with the South Lake Union line, opened January 23rd. The 2.5-mile-long project was installed at a cost of $134 million.

New Orleans — The Regional Transportation Authority’s 1.6-mile North Ramparts-St. Claude Streetcar Line Project, budgeted at $40-41 million, is nearing completion, with opening expected this summer or early fall.

El Paso — The city’s 4.8-mile heritage streetcar line project, budgeted at $97 million, is now under way, with the legacy fleet of stored historic PCC cars now being renovated and restored by Brookville Equipment Corp.

Oklahoma City — A 4.6-mile, $129-million streetcar starter line project continues to proceed, with rolling stock supplier designated as Brookville Equipment Corp.

Milwaukee — The city’s 2.1-mile, $124-million downtown streetcar starter line project is now well under way.

Detroit — The 3.3-mile, $140-million M-1 streetcar project, mainly routed on the city’s iconic Woodward Avenue, continues to move ahead.

Kansas City — The 2.2-mile-long, $102-million project is nearing completion, and expected to open in a few months.

Cincinnati — The city’s 1.8-mile, $148-million core area streetcar project (see photo at top of post) is nearing completion, and expected to open this fall.

Washington, DC — Officials are now hoping the problem-plagued, long-delayed 2.2-mile H St.-Benning Rd. streetcar project, costing approximately $200 million so far, will at last be completed and able to open within a few weeks.

Tucson — The city’s 3.9-mile Sun Link streetcar starter line, opened in 2014 at an investment cost of about $199 million, continues to exceed its ridership projections.

Atlanta — The 2.7-mile-long Peachtree district streetcar starter line, completed at a budget of $93 million, also opened in 2014. ■

DIY planning for light rail!


LRT car clearances profile (excerpted from presentation).

LRT car clearances profile (excerpted from presentation).


Interested in designing a conceptual light rail transit (LRT) line for your own community? If you’ve been wishing you had something like a Do-It-Yourself (DIY) planning manual or set of basic guidelines for doing that, a report presented to the 13th National Light Rail & Streetcar Conference (co-sponsored by Transportation Research Board and American Public Transportation Association, and held last month in Minneapolis, Minnesota) may be just what you need.

Titled «Developing Infrastructure-Relevant Guidelines for Preliminary Conceptual Planning of a New Light Rail Transit System», the report has been prepared by Urban Rail Today principal Lyndon Henry (also a technical consultant for the Light Rail Now Project, and a Railway Age online writer). As the abstract indicates, the report represents a step toward publishing “readily accessible guidelines to provide a resource for developing conceptual design and evaluation plans, particularly involving infrastructure and fleet requirements, for new light rail transit (LRT) systems in their communities.”

Links to the original paper and PowerPoint presentation are available (both as PDFs). ■

Cincinnati hosts APTA streetcar events


John Schneider, Cincinnati's "Mr. Streetcar" and a co-principal of Urban Rail Today. (Photo: L. Henry.)

John Schneider, Cincinnati’s “Mr. Streetcar” and a co-principal of Urban Rail Today, addresses APTA Streetcar Committee meeting on Dec. 15th. Photo: L. Henry.

Cincinnati, Ohio — Roughly a hundred streetcar planning and development professionals — including Urban Rail Today co-principal Lyndon Henry — converged here in mid-December to attend a business meeting and technical tours sponsored by the Streetcar Subcommittee of the American Public Transportation Association (APTA). The main meetings spanned two days (15-16 December 2014), covering topics ranging from technical issues to the nuts-and-bolts of Cincinnati’s long political saga, navigating through public referendums and electoral permutations to finally secure the streetcar project now fully under construction. A highlight of the meetings was a presentation by John Schneider, Cincinnati’s “Mr. Streetcar” (see photo at top of this post), who chronicled and explained Cincinnati’s convoluted path to a rail transit system. (John is also a co-principal of Urban Rail Today.)

But special tours were also a major highlight of the APTA event, including a Dec. 14th tour of Cincinnati’s “subway-that-never-ran”, the remnants of subway tunnels beneath the center of the CBD. Built after World War I and into the 1920s, but eventually abandoned when city leaders scuttled the project, the subway is a creepy, sad, but fascinating artifact of urban industrial archaeology, with ghostly stairways, waiting platforms, and ticket kiosks constructed for passengers that would never come, and stringers ready for tracks that were never laid and trains that never ran. (Municipal bonds were not finally paid off till the 1960s — a kind of object lesson in the drawbacks of lack of perseverance and excessive misplaced frugality.)

For more information, history, maps, and photos, see:

Cincinnati’s Abandoned Subway — history and photos

Zach Fein (Cincinnati architect and photographer) — excellent modern photos

Cincinnati’s Abandoned Subway — link to PBS documentary available on Amazon.com


APTA tour group walking through darkness of Cincinnati's never-finished subway on morning of Dec. 14th. (Photo: L. Henry.)

APTA tour group walking through darkness of Cincinnati’s never-finished subway on morning of Dec. 14th. Photo: L. Henry.


Most of Cincinnati’s modern streetcar starter line project is now under construction, and particular features were inspected via another APTA Streetcar Committee tour on Dec. 16th. It’s a roughly 1.8-mile route, end to end, with about 3.6 miles of track and 17 stations. As the map below illustrates, the route has a sort of elongated “Figure 8” configuration, forming a long, narrow loop with tracks for each direction on parallel streets — no double track.


Map of Cincinnati's Phase 1 streetcar project, the first phase of hopefully a much larger urban rail system for the city. Map: City of Cincinnati.

Map of Cincinnati’s Phase 1 streetcar project, the first phase of hopefully a much larger urban rail system for the city. Map: City of Cincinnati.


In the middle segment where the alignment runs east-west for a short distance, the bottom (southern) track is routed in the median of Central Parkway, and the upper (northern) track along 12th St. Central Pkwy. was constructed atop the site of an old canal, and it was this canal that got drained and converted into the ill-fated subway that never opened.

Cincinnati’s famous Over-the-Rhine (OTR) district is the area above (i.e., north of) Central Pkwy. The district once was home to a substantial population of German immigrants who dubbed the old canal the “Rhine”. The area declined over the many decades since the subway debacle and the rustbelt decline of Cincinnati, but the neighborhoods adjacent and near to the streetcar line are experiencing quite a revival.

Streetcar rolling stock is being supplied by the Spanish railcar manufacturer CAF through their U.S. subsidiary CAF USA. Five cars for the starter line will be the first 100% lowfloor streetcars deployed in America (see simulation graphic below). Each will be 23.6 meters (77.4 feet) long, with four doors per side, 32 seats, and a total capacity of 154 passengers. Up to 6 bicycles can also be accommodated in the car.


CAF Urbos 3 streetcar for Cincinnati. Top: Interior. Bottom: Exterior. Graphic: CAF.

CAF Urbos 3 streetcar for Cincinnati. Top: Interior. Bottom: Exterior. Graphic: CAF.


CAF’s Urbos 3 car is actually a fully robust light rail transit (LRT) car adapted for streetcar application. The cars are double-ended (i.e., bidirectional) with a maximum speed capability of 70 km/h (about 43 mph).

As illustrated in the photo below, the streetcar project is being constructed predominantly with curbside tracks and stations that simply protrude outward from the sidewalks.


Members of APTA Streetcar Committee inspect streetcar station-stop under construction on Walnut St. in Cincinnati CBD. Photo: L. Henry.

Members of APTA Streetcar Committee inspect streetcar station-stop under construction on Walnut St. in Cincinnati CBD. Photo: L. Henry.


The photo below shows a completed section of track next to a station in the OTR district. The track diverges slightly toward the station platform, in part to minimize clearance needed for the platform edge and to maximize clearance with respect to the parking lane.


Completed section of streetcar track veers slightly toward station platform. Photo: L. Henry.

Completed section of streetcar track veers slightly toward station platform. Photo: L. Henry.


The use of recycled cobblestones to embed some sections of the track is shown in the photo below. This kind of treatment (if other motor vehicle lanes are left smooth) may tend to dissuade motorists from excessive running in the streetcar lane, giving it a bit of the quality of a semi-dedicated lane…


Section of streetcar track embedded in cobblestone paving. Photo: L. Henry.

Section of streetcar track embedded in cobblestone paving. Photo: L. Henry.


The system’s initial carbarn (storage-maintenance-operations facility) is under construction at the north end of the current route, at Henry St. The photo below, looking south, shows the main building and part of the storage yard. While the system will start with just five cars, the facility has space for 13. The revenue track wraps around on Henry St., on the carbarn’s north side (i.e., behind the camera in the photo below) to effectively reverse direction and head southbound.


Carbarn main building and portion of streetcar storage yard under construction. Photo: L. Henry.

Carbarn main building and portion of streetcar storage yard under construction. Photo: L. Henry.


In the photo below (facing north, toward Henry St.), track workers are performing thermal welds on one of the fan tracks leading into the carbarn. The street just beyond them is Henry St., which streetcars will use to turn from northbound to southbound and thus loop around the carbarn.


Workers performing thermal weld on track leading into carbarn storage yard. Photo: L. Henry.

Workers performing thermal weld on track leading into carbarn storage yard. Photo: L. Henry.


Cincinnati’s streetcar project is clearly not only well on its way, but planners are already scoping out the next extension, reaching further north to the University of Cincinnati. Furthermore, with a system designed for and deploying fully capable LRT rolling stock, an eventual transformation of the basic streetcar system into a faster, high-capacity LRT system is a distinct possibility for the future. ■

Austin’s urban rail loss boosts push for new light rail Plan B


Proposed alternative Plan B for Austin's Guadalupe-Lamar corridor would also have branch serving re-purposed Seaholm power plant site and Amtrak station. Graphic: Project Connect.

Proposed alternative Plan B for Austin’s Guadalupe-Lamar corridor would also have branch serving re-purposed Seaholm power plant site and Amtrak station. Graphic: Project Connect.

By Lyndon Henry

Austin, Texas — Sometimes there are rail transit plans (and other urban development proposals) that are just plain misguided and potentially deleterious to a city’s best interests. That was the case with the urban rail scheme proposed for Austin, resisted by some of the city’s most dedicated and savvy rail advocates, and rejected by voters on Nov. 4th by a 14-point margin, 57% Against to 43% In Favor.

Counterintuitive though it may seem, this was not only a huge success for transit advocacy but also a major victory for rail development in Austin. The official plan, developed via a disastrously flawed study by a multi-agency consortium called Project Connect, would have committed $1.4 billion to a 9.5-mile “urban rail” line (a local proxy term for light rail transit, or LRT) in a virtually non-existent corridor, running from a northern site called Highland through the east side of the city’s core, across the Colorado River, to a southeastern terminus on East Riverside Drive. (The Nov. 4th ballot measure asked voters to approve $600 million of General Obligation bonds for the urban rail plan, with the assumption that the remainder would be covered by federal grants and other sources.)

Not only was it a seriously flawed route, but it was also seriously over-designed (I called it “gold-plated”). Encountering formidable alignment challenges (e.g., constricted rights-of-way, sharply tortuous curves, a river crossing, and an in-roadway crossing over I-35), the proposal called for a pricey “signature bridge” and a $230 million subway for which the need was in dispute. As a result, the plan would have calculated as the third most expensive LRT starter line in U.S. history. And that massively wasteful encumbering of local funding capability would have, in effect, “sucked the oxygen” from local resources and strangled further rail development and expansion.

But high cost wasn’t the worst problem with the Highland-Riverside proposal (after all, even a good, cost-effective plan could have a high pricetag). Instead, mobility needs were virtually sidelined in deference to local development objectives (and these were basically misguided). Fundamentally, the plan ignored the city’s most central heavy-traffic local corridor, defined by two major arterials named North Lamar Blvd. and Guadalupe St., which funnels major travel from the northwest, north, and northeast through several miles of activity concentrations and finally into the Core Area — the University of Texas, state Capitol Complex, and Central Business district (CBD).

Potential daily LRT ridership serving this corridor has been assessed in the range of 30,000 to 40,000 — roughly 2-3 times that of the now-defunct Highland-Riverside plan. And this relates directly to urban development: By and large, developers will invest and build where the ridership is. Mobility is the key — provide a solid mobility project, and development will follow.

In any case, urban rail must first and foremost make bona fide mobility sense as well as meet appropriate urban development needs. Urban rail shouldn’t be intended as just a pricey amenity to enhance urban development.

That’s where Project Connect’s rail plan fell way short. But, in contrast, what has all the hallmarks of a real winner of an extremely cost-effective alternative plan is emerging to take its place, this time in the crucial Guadalupe-Lamar corridor. Currently referred to as Plan B, the latest version of this alternative proposes a 6.8-mile LRT starter line running from the major North Lamar Transit Center at U.S. 183 into the Core Area. Along the way, the line would connect with Austin’s existing MetroRail regional passenger rail service and serve a spectrum of major commercial and residential developments, established neighborhoods, and activity centers — plus the West Campus, with the third-highest residential density in Texas. All of this was missed by Project Connect’s plan. See: A “Plan B” proposal for a Guadalupe-Lamar alternative urban rail starter line.

Plan B LRT line would stretch 6.8 miles from a major transit center on the north to the CBD, with a branch west to the Seaholm-Amtrak development site. Map: Austin Rail Now.

Plan B LRT line would stretch 6.8 miles from a major transit center on the north to the CBD, with a branch west to the Seaholm-Amtrak development site. Map: Austin Rail Now.

This version of Plan B LRT for Guadalupe-Lamar also includes a branch from downtown west to a major development site at the city’s former Seaholm power plan, adjacent to the Amtrak train station (a connection originally proposed by Project connect but missing in the final 9.5-mile highland-Riverside plan).

In addition to striking the right balance between meeting mobility needs cost-effectively and catalyzing desirable development, there’s an additional major lesson to be gleaned from Austin’s recent urban rail planning and voting experience: Connect with the grassroots community.

Much of the Austin community’s discontent with Project Connect’s “study” process (mainly from June through December 2013) resulted from a sense of alienation from the process and the proposed plan that emerged from it. Project Connect claimed a vigorous “public participation” program, with dozens and even hundreds of “meetings”. But, rather than true community meetings, facilitating bona fide discussion and community decisionmaking, and enabling various segments of the community to interact with one another, the official “participation” process mainly involved presentation events, with project personnel unveiling decisions reached in seclusion by the project team. Members of the community, excluded from this process, were typically given the opportunity merely to select among a handful of choices; meanwhile, the major structure and contours of the plan were determined by political officials and project team staff.

Hopefully, this will change substantially — particularly with a new, expanded City Council, elected via a new district structure. Community activists and rail transit advocates have been interacting with new political leaders in an effort to institute a more democratic process with grassroots representation and participation directly in the development of plans.

Perhaps this kind of grassroots process will materialize in a way to shape and advance the prospects of Plan B light rail for Guadalupe-Lamar.

For more analysis of Austin’s recent urban rail planning and vote, see the following articles:

Austin: Flawed urban rail plan defeated — Campaign for Guadalupe-Lamar light rail moves ahead
http://austinrailnow.com/2014/11/05/austin-flawed-urban-rail-plan-defeated-campaign-for-guadalupe-lamar-light-rail-moves-ahead/

Lessons of the Austin rail bond defeat
http://austinrailnow.com/2014/11/20/lessons-of-the-austin-rail-bond-defeat/

Austin urban rail vote fails, alternative light rail plan proposed
http://www.examiner.com/article/austin-urban-rail-vote-fails-alternative-light-rail-plan-proposed

Austin: After urban rail plan failure, opponents spar over a “Plan B”
http://www.examiner.com/article/austin-after-urban-rail-plan-failure-opponents-spar-over-a-plan-b

Austin urban rail plan: Behind voters’ rejection
http://www.railwayage.com/index.php/blogs/lyndon-henry/austin-urban-rail-plan-behind-voters-rejection.html

Austin: As urban rail vote fails, campaign for Plan B light rail rises
https://lightrailnow.wordpress.com/2014/11/30/austin-as-urban-rail-vote-fails-campaign-for-plan-b-light-rail-rises/

Detroit’s M-1 modern streetcar project gets under way


Artist's rendition of how the streetcar operation may look on Woodward Avenue when it's completed. Graphic: M-1 Rail.

Artist’s rendition of how the streetcar operation may look on Woodward Avenue when it’s completed. Graphic: M-1 Rail.

Detroit, Michigan — As tracklaying begins on this city’s key central arterial, Woodward Avenue, the M-1 Rail project at last seems to actually be getting under way.

2_URT_det-lrt-stc-map-prop-rte_M-1-ProjThe 3.3-mile, $136 million project, financed by a combination of government and private sources, would in effect restore a tiny fragment of Detroit’s once-extensive urban streetcar system. The Woodward line carried the heaviest ridership in the system.

At a Sep. 15th ceremony announcing an additional $12.2 million federal grant for the project, U.S. Secretary of Transportation Anthony Foxx hailed Detroit’s determination and its urban rail project as a major step forward in helping Detroit get back on its feet (reported in CBS Detroit):

What we saw with this M1 project … was again the strength, determination and mettle of a great city that has a vision not only of a transportation asset that takes people to jobs, but in fact one that brings jobs to the people by revitalizing a critical part of Detroit.

Even Michigan Governor Rick Snyder, a conservative Republican, applauded the project as “an opportunity partnership”, affirming that “This is an opportunity to strengthen the city and the state by creating something that is going to bind midtown and downtown together in a fabulous way.”

Following those remarks, M-1 Rail officials announced a list of major sponsors for stations planned along Woodward. These included such well-known corporate names as the Henry Ford Health System, Penske, the Ford Motor Corp., the Chrysler Foundation, JP Morgan Chase & Co., Chevrolet, the BlueCross BlueShield Association, and Quicken Loans. ■

Beware the “BRT” snake oil


0_ARN_logo-SnakeOil-label_WEAresearch-com-au

Just about anyone who’s raised the possibility of light rail transit (LRT, the most popular form of urban rail) for their community has probably encountered a familiar pitch for “bus rapid transit” (BRT): Why not try “BRT” instead? It’s just like light rail, but cheaper…

The problem with this isn’t that better bus service is a bad idea. Upgraded buses, upgraded bus stops, traffic signal priority, high-tech innovations such as “next bus” passenger information systems at bus stops and onboard wi-fi, and other improvements, are all important ways to attract more ridership to public transport.

But the problem is that a collection of “BRT” promoters — from the motor bus industry to highway enthusiasts to some self-proclaimed transit supporters, have been claiming that, somehow, “BRT” has all the advantages of urban rail at much lower cost. And that’s just plain wrong. It’s false, and in many, perhaps most, cases, it’s deceptive. In effect, it’s a kind of snake oil being peddled in the field of urban transit.

An awful lot of cities and transit systems worldwide that have been vigorously installing new LRT systems (including streetcars) haven’t been ignorant or oblivious to the “BRT” option. Instead, they’ve reviewed and analyzed the pros and cons of this and other alternatives, and concluded that, for their own needs, LRT — and other forms of urban rail — is the best choice.

Let’s briefly consider a few of the most familiar claims that “BRT” proponents try to promulgate.

► “BRT” is truly “rapid transit” — Mostly nonsense. The “BRT” promotion campaign typically presents images of buses on special exclusive guideways (the so-called “Gold Standard” of BRT) to seduce public support (mainly from local civic leaders). But the reality of most purported “BRT” systems is … buses running mostly in mixed traffic like “regular” buses, but perhaps in limited-stop modes, with somewhat fancier stations … but a far cry from fully grade-separated rapid transit.

This has become an issue in Austin, Texas with perhaps the most recently opened so-called “BRT” system (funded as “BRT” under the federal Small Starts program). Called MetroRapid, the system is being widely ridiculed in the community for attracting daily ridership of only 6,000 and resulting in a net ridership loss of 11% in the corridor it serves. See: Why MetroRapid bus service is NOT “bus rapid transit”.

Austin's MetroRapid "BRT" systems runs in mixed traffic, and has become the object of local ridicule. Photo: L. Henry.

Austin’s MetroRapid “BRT” systems runs in mixed traffic, and has become the object of local ridicule. Photo: L. Henry.

► “BRT” is a lot cheaper than LRT — Well maybe, maybe not. When total lifecycle costs, expressed as annualized capital costs, plus operating and maintenance (O&M) costs are considered, LRT is often the more cost-effective investment, particularly through the essential metric of cost per passenger-mile.

This issue is analyzed in a number of articles on the Light Rail Now website; see, for example:

Light Rail Lowers Operating Costs

How Light Rail Saves Operating Cost Dollars Compared With Buses

Streetcar vs. Bus: Operating cost comparison

“Free” buses vs. “expensive” rail?

Portland: New Yellow Line LRT on Interstate Ave. covers capital investment from operating cost savings and benefits

Brisbane Reality Check: The high cost of “cheap” busways

► “BRT” attracts as many riders as LRTCertainly not on average. Overall, LRT systems beat all types of bus systems in meeting ridership goals and attracting “choice” riders (who have the option of using private motor vehicles). Some evidence is provided in the following articles:

Rail Transit vs. “Bus Rapid Transit”: Comparative Success and Potential in Attracting Ridership

Research Study: Riders Prefer Light Rail to “Bus Rapid Transit”

Motorists prefer light rail over buses, reports UK poll

► “BRT” has the capacity of LRTDefinitely not in terms of ultimate potential capacity. As “BRT” systems attempt to cope with increasing ridership (which may happen not because “BRT” systems are so attractive, but because of rising population and the increasing costs and congestion of private motor vehicle systems), the number of buses required to try to provide capacity starts to overwhelm road systems and station passenger-handling capacity.

Massive bus traffic jam in Brisbane, Australia illustrate problem of fitting "BRT" into a high-capacity application. Photo: James Saunders.

Massive bus traffic jam in Brisbane, Australia illustrate problem of fitting “BRT” into a high-capacity application. Photo: James Saunders.

► “BRT” attracts development, just like LRTFalse. This claim by “BRT” advocates is based predominantly on cases in Pittsburgh and Cleveland, In both cities, the real estate development attributed to “BRT” was overwhelmingly attracted by rail transit systems, both existing and planned.

► “BRT” is just like LRT, but cheaperDefinitely, totally false. Basically, you get what you pay for. “BRT” fails to offer the speed (for similar routes and station spacing), ride comfort, reliability, accessibility, lower energy consumption, lower environmental impact, cost-effectiveness, and urban livability of LRT. Here are some articles that provide evidence for this:

New light rail projects in study beat BRT

Reality Check: Breakthrough Technologies Institute’s Dubious Claims on “Bus Rapid Transit”, Electric Rail, and Global Warming

LA’s “Orange Line” Busway – “Just Like Rail, But Cheaper?” A Photo-Report Reality Check

There are other issues in this comparison which merit being covered. We’ll examine some of them in future posts. ■

Phoenix light rail transit (LRT, left); Los Angeles Orange Line "bus rapid transit" (BRT, right). Photos: L. Henry.

Phoenix light rail transit (LRT, left); Los Angeles Orange Line “bus rapid transit” (BRT, right). Photos: L. Henry.

Kansas City streetcar procurement “piggybacks” on Cincinnati’s CAF order


CAF Urbos 3 streetcar for Kansas City. Graphic: CAF.

CAF Urbos 3 streetcar for Kansas City. Simulation: CAF.

Kansas City — By “piggybacking” its order for streetcar rolling stock on Cincinnati’s order, Kansas City has probably saved at least several million dollars in the cost of its streetcar project.

This past October, Kansas City took advantage of the “piggybacking” opportunity and awarded a $22 million contract to CAF USA, a subsidiary of Spain’s Construcciones y Auxiliar de Ferrocarriles S.A., for five streetcars to provide service over its 2.2-mile downtown streetcar starter line, now under construction. (For background, see Kansas City — Another new downtown streetcar project starts to take shape.)

The Urbos 3 streetcars, costing a relatively bargain price of roughly $4.4 million each, will be assembled at CAF’s plant in Elmira, N.Y. The order follows (and is linked to) CAF USA’s contract with Cincinnati, which also involves five streetcars. (Thanks to Railway Age for details.)

Via a Twitter message link from John Schneider, here’s a look at CAF’s Urbos 3 streetcar running in Spain:


Hopefully, within a few years we’ll see a very similar model running on the streets of Cincinnati and Kansas City.

Cincinnati: “Our city confirmed its will to continue along path to a balanced transportation system”


Cincinnati: Simulation of streetcar running downtown. Graphic: City of Cincinnati.

Cincinnati: Simulation of streetcar running downtown. Graphic: City of Cincinnati.

By John Schneider

This commentary has been adapted from a December 19th statement by the author to supporters of the campaign to continue Cincinnati’s streetcar project, immediately after the favorable vote by the City Council.

With the City Council’s vote on December 19th to resume Cincinnati’s streetcar project, our city confirmed its will to continue along the path to a balanced transportation system. Our path has been up and down with lots of twists and turns and leaps of faith that took us to unknown places. But we soldiered-on, and now the path is wider, flatter, and clearly marked for others to follow, not only in Cincinnati but in other cities that want to gain more citizens and become more competitive.

There are so many people to thank, but first and foremost, I want to thank former Mayor Mark Mallory, Vice Mayor Roxanne Qualls, and City Manager Milton Dohoney. Even though we reached our goal on December 19th, we wouldn’t have even been in the game were it not for their leadership of the Cincinnati Streetcar over many years. Their support cost them dearly, and we should be forever grateful.

And to our long-time champions on City Council — Chris Seelbach, Yvette Simpson and Wendell Young whose eloquence and persistence following the election, working with PG Sittenfeld, brought their colleagues, Vice Mayor David Mann and Councilmember Kevin Flynn, along to enable us to continue along our path.

Immediately after the December 19th vote, Mayor John Cranley was very gracious in offering his congratulations to me and to others. I hope this period of divisiveness now passes and that we can all join with him and Christopher Smitherman, Charlie Winburn, and Amy Murray to foster the city we all want to have.

Were it not for Ryan Messer, who parachuted-in to lead this effort in early November, we would not have succeeded. The kind of leader who emerges every ten years or so here, he brought new energy to our movement. Early-on, he recruited our attorney, Paul DeMarco, who used his contacts at the highest level of our nation’s government to bring about the results we achieved, to assure the Feds we knew where we were going. Early-on, without a hint of hesitation, Karen Blatt volunteered our spiffy campaign office, and Ryan hired Scott Allison to execute the flawless campaign to gather signatures. Others including Jean-Francois Flechet, Sean Lee, Rob Richardson, Jr, Margy Waller and Brad and Karen Hughes did whatever had to be done and were the wisest advisors and best team-players anyone could have.

There are so many others that contributed so much to this effort that I cannot mention them all but they are all strongly appreciated. Suffice it to say that this effort could not have been sustained over all these years without all the people who have been involved.

Eric Avner of the Haile Foundation raised $9,000,000 in a little over 48 hours, enough to make City Council comfortable that the cost of operating the streetcar was assured for the first ten years. This was the keystone of the plan to save the streetcar.

There were many memorable moments in this campaign. One I’ll never forget was the December 10th meeting at First Lutheran Church near 12th and Race, where 450 people showed up to sign-out their petitions. Chris Heckman and Kristen Myers are members of the congregation, and they quickly arranged for the church to open its doors twice to us. I’m certain this set the tone for the whole campaign.

John Schneider photo

John Schneider, Cincinnati’s “Mr. Streetcar”. Photo: Cincinnati.com.

Speaking of the campaign, we now have 11,000 Cincinnatians’ names and addresses for our efforts going forward. The planning and execution of the signature-gathering was orchestrated with great precision by The Strategy Group and its able leader, Ian James, who made a critical judgment that the number and intensity of our volunteers was more than adequate to gather the signatures. We wouldn’t need paid signature-gatherers. Plus, it gave us all an opportunity to tell the streetcar’s story in the way we know it. And by the way, we registered a bunch of streetcar supporters to vote in the process.

Our thanks go well beyond Cincinnati to the many people in many cities who have been watching our project intently, including especially Portland’s mayor, Charlie Hales and his wife Nancy, who have joined us on many of our trips there over the years. When he was in the private sector, Charlie helped plan the Cincinnati Streetcar, and he has been a guiding light for me. We’re not finished with the Portland trips. They have an early spring there.

Most of all, we should all thank our spouses, families, employers and co-workers for tolerating our absences over the past days and nights. They were soldiers in this too.

I hope that in this new year everyone will continue to work harder than ever to bring more diverse transportation choices to our city, Cincinnati, or to whatever city where you live.

Tucson: Streetcar Celebration builds public anticipation of urban rail line opening


Tucson streetcar leaves center-street station during testing. Photo:  Tyler Baker, Arizona Daily Wildcat.

Tucson streetcar leaves center-street station during testing. Photo: Tyler Baker, Arizona Daily Wildcat.

Tucson, Arizona — It’s still many months away, but public anticipation of the opening of Tucson’s brand-new streetcar system has been building. And it’s getting a huge boost from the local Friends of the Streetcar group.

In collaboration with merchants at Main Gate Square outside the main entrance to the University of Arizona, the pro-streetcar group is sponsoring Streetcar Celebration: Destination Main Gate Square, a special celebration on January 15th, one of several shindigs the organization has been initiating to raise awareness and feed anticipation for the new service.

The 3.9-mile, $196 million modern streetcar line is due to open in mid-2014 after rolling stock supplier United Streetcar delivers all eight streetcars on order.

The upcoming festivities, scheduled on a Wednesday afternoon between 4:00 and 7:00 pm, will include performances by musical groups, a street performance group called Cirque Roots (featuring stilt walkers, hoop dancers, and acrobats), “fun with 2-EEE the Clown Face Painting and Balloons, a free photo booth by Bumblebee Photobooth with souvenir photos and more”, according to a report in The Explorer, a local publication. The Arizona State Museum will be open until 7:00 pm allowing free admission, and a number of restaurants, cafes, and various retailers are offering substantial discounts.

With opening of the new urban rail system scheduled for much later in the year, these events in Tucson by local rail supporters may provide an example of how to build public enthusiasm for the service — and hopefully pay off in higher ridership when the trains actually start rolling.

Merry Christmas, Cincinnati! Streetcar project resumes work


Cincinnati streetcar on order from builder CAF. Simulation: City of Cincinnati.

Cincinnati streetcar on order from builder CAF. Simulation: City of Cincinnati.

For supporters of urban rail, it’s been a clenched-teeth political action movie in Cincinnati, as newly elected Mayor John Cranley tried to implement his campaign promise to pull the plug on the city’s streetcar project — even though construction was well under way, tracks had already been laid in the street, and the Federal Transit Administration (FTA) was threatening to demand repayment of of millions of dollars in grants if the project were cancelled.

Besides the new mayor, the election of three new councilmembers meant a council majority against the rail project, and on December 4th, the council voted to “pause” further work pending an independent audit by consulting firm KPMG. In response, the FTA issued an ultimatum: Resume the project by Dec. 19th, or forfeit the federal grant and pay back funds already transferred.

Meanwhile, the prospect of scuttling an ongoing project and wasting funds already invested sparked a local grassroots rebellion involving not just rail project supporters but a wider spectrum of Cincinnatians. A powerful mobilization for a referendum on a city charter change to require completion of the rail project collected roughly twice the number of signatures required — also attracting national media attention. This show of force seems to have helped in starting to move councilmembers’ leanings.

Recently laid Cincinnati streetcar trackage in Elm St. on Nov. 8th. Original granite pavers are being reinstalled to restore historic appearance. Photo: Travis Estell (Flickr).

Recently laid Cincinnati streetcar trackage in Elm St. on Nov. 8th. Original granite pavers are being reinstalled to restore historic appearance. Photo: Travis Estell (Flickr).

In addition, as described by a New York Times article (Dec. 22nd), “KPMG’s audit showed that completing the line would cost the city $68.9 million; canceling would run between $16.3 million and $46.1 million, not including the potential costs of litigation, which could be astronomical.” Thus, noted the Times, streetcar proponents were able to argue that “The city could spend millions of dollars and have a streetcar with the potential for return on investment, or have nothing to show for it while facing a tangle of lawsuits ….”

On the brink of the Dec. 19th deadline, the project was also reprieved by a written commitment, honchoed by the Haile U.S. Bank Foundation and involving roughly 15 private-sector backers, to cover as much as $9 million of the line’s operating costs over its first decade, if necessary.

On Dec. 19th, just hours from the FTA deadline, the Cincinnati city council voted 6-3 to resume the project. “We’re going to have a streetcar” Mayor Cranley announced at an afternoon news conference with new Councilman Kevin Flynn, who had spent days helping forge the private financing agreement.

It represented an amazing victory for the broad swath of Cincinnati streetcar supporters, who had turned out by the hundreds to gather many thousands of signatures on the referendum petition. It’s also recognized as a huge victory for rail advocacy and for urban livability, and a terrific model for communities throughout North America.

According to the Cincinnati Business Journal (Dec. 23rd), Work on the project resumes on Dec. 26th, with delivery of an additional set of rails on Elm St., and “The installation of rails will be underway again on Friday, as crews restart their jobs north of Findlay Market.”

More details on this issue are summarized in a recent online article on the Railway Age magazine website:

Cincinnati streetcar survives political turmoil

Another Railway Age article by Urban Rail Today co-principal Lyndon Henry draws a parallel between citizens’ efforts for urban rail in Austin, Texas and those in Cincinnati:

Cincinnati and Austin: Community urban rail proponents challenge City Hall