Atlanta — Streetcar due to open next spring


Simulation of Atlanta's Peachtree St. streetcar. Graphic: Railway Preservation.

Simulation of Atlanta’s Peachtree St. streetcar. Graphic: Railway Preservation.

Atlanta, Georgia — Completion of Atlanta’s streetcar project (called a “loop” because, to provide two-way service, it consists of single-direction lines running on roughly parallel streets that form elongated loops) is just about six months away from its scheduled opening in the spring of 2014, according to an Oct. 14th report in the Atlanta Curbed blog.

As Urban Rail Today reported in the earlier article Atlanta Streetcar construction pushes forward (25 February 2013), the total route of the streetcar starter line is 2.62 miles, with a project cost of about $93 million. It would re-install a tiny fragment of the urban area’s once-extensive network of nearly two dozen urban and several interurban surface electric railway lines, the last of which was scrapped in 1949.

Streetcar trackage under construction in Ellis St., summer 2013. Photo: Central Atlanta Progress.

Streetcar trackage under construction in Ellis St., summer 2013. Photo: Central Atlanta Progress.

Looking to the future … the new modern streetcar line, designed to carry passengers between Centennial Olympic Park and the King Historic District, has 12 station-stops, with headways projected to be 15 minutes between trains. Ridership is projected at 2,600 per weekday.

All rides will be provided for free for the first three months of operation. After that, according to the blog post, fares will initially be just $1.00, “until MARTA upgrades its Breeze Card system to accommodate the light-rail route. Transfers from MARTA will be free.”

According to the project’s executive director, Tim Borchers, construction is now on time (overcoming earlier delays) and $2 million under budget.

Borchers, a streetcar expert from Australia, long respected in the U.S. rail transit industry, is extremely bullish on the potential benefits of the streetcar system. In an interview with Atlanta’s WABE-FM, he assured listeners: “It’s been happening all over the world. Streetcar systems are being used to rebuild decaying urban cores, give a financial boost to cities, relieve traffic, help the environment, and also, of course, provide public transportation.”

How Portland’s light rail trains and buses share a transit mall


LRT train on Portland's 5th Ave. transit mall swings to the curbside station to pick up waiting passengers. Photo: L. Henry.

LRT train on Portland’s 5th Ave. transit mall swings to the curbside station to pick up waiting passengers. Photo: L. Henry.

♦ How can both buses and light rail transit (LRT) trains share the same transit-priority paveway or street? There are numerous examples that answer this, but certainly one of the best is in Portland, Oregon — the 5th and 6th Avenue transit malls.
Recently, the Austin Rail Now (ARN) blog posted an article focusing on Portland’s transit malls, and because of the more general usefulness of this information for many more communities, we’re re-posting it here with the kind permission of ARN. (It’s also been re-posted by the Light Rail Now blog.)
The opening context for the article is the urban rail planning project currently under way by the City of Austin, Capital Metro (the transit authority), and a transit planning consortium called Project Connect. Transit priority lanes are now being installed on two major downtown north-south streets, and it’s been expected that urban rail trains would share these with buses, including the MetroRapid premium-bus services now being implemented in several major city corridors. However, some transit advocates are noting that these lanes may have insufficient capacity to handle all the bus routes plus MetroRapid, much less adding LRT into the mix.
Portland’s experience thus provides an illustration of how LRT trains and buses can share a priority alignment in a way that works well.

Capital Metro and the City of Austin have a project under way to designate “Transit Priority Lanes” on Guadalupe and Lavaca Streets downtown between Cesar Chavez St. and MLK Jr. Blvd. It’s mainly to expedite operation of the planned new MetroRapid bus services (Routes 801 and 803), but virtually all bus routes running through downtown will also be shifted to these lanes, located on the far-righthand side of traffic on each street (i.e., the righthand curbside lanes).

According to a 2011 study funded by the City of Austin, the Official (City + Project Connect) Urban Rail route is also envisioned to use these lanes downtown. Alternatives to the Official plan have also assumed that these routes would be available for alternative urban rail lines serving the Guadalupe-Lamar corridor.

However, there are legitimate questions as to whether these two lanes could simultaneously and effectively accommodate the two MetroRapid bus routes (10-minute headways each) plus all other Capital Metro routes (various headways) as well as urban rail (10-minute headway), all running in both directions.

Experience with both light rail transit (LRT) trains and buses sharing the same running way is rare in the USA, but one of the best examples can be seen in Portland, Oregon. For years, 5th and 6th Avenues through the downtown have been used by multiple bus routes as a transit mall, with a single lane provided for general motor vehicle access. In September 2009 LRT was added with the opening of the new Green Line; see: Portland: New Green Line Light Rail Extension Opens.

The integration of LRT with bus service in the 5th and 6th Avenue transit malls has worked well. Here’s a brief photo-summary illustrating some of the configurational and operational details.

• Buses and LRT trains share transitway

This illustrates how both bus services and LRT trains share the mall. Tracks, embedded in the pavement, weave from curbside to the second lane over. A third lane is kept open for mixed motor vehicle traffic.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

• LRT routes cross

This photo shows how the Green and Yellow LRT lines on the 5th Ave. transit mall cross the Red and Blue LRT lines running on 5th St. You’re looking north on 5th Ave., and just across the tracks in the foreground, the LRT tracks on 5th Ave. weave from the middle of the street over to the curbside, where a station-stop is located. This allows LRT trains to access stations but otherwise pass buses stopped at bus stops on the same street.

Portland 5th Ave. transit mall. Photo: L. Henry.

Portland 5th Ave. transit mall. Photo: L. Henry.

• LRT train leaving station

Here an LRT train has just left the curbside station, following the tracks into the middle lane of the street. This track configuration allows the train to pass a bus boarding passengers at a stop.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

• LRT train passing bus

Another train moves to the street center lane and passes the bus stop. Meanwhile, other buses queue up at the street behind.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

Portland 5th Ave. transit mall. Photo: Dave Dobbs.

• Bus bunching

Buses are prone to “bus bunching” (queuing) in high-volume situations because of their smaller capacity, slower operation, slower passenger boarding/deboarding, difficulty adhering to schedule, etc. However, notice how they’re channeled to queue up in a lane off the LRT track.

Portland 5th Ave. transit mall. Photo: L. Henry.

Portland 5th Ave. transit mall. Photo: L. Henry.

Can and will Austin and Project Connect planners learn anything about how to create workable Transit Priority Lanes from examples like this? Time will tell…

Getting the streetcar route right in Cincinnati


Another simulation view of the CAF streetcar on order for Cincinnati. Graphic: CincyStreetcar blog.

Another simulation view of the CAF streetcar on order for Cincinnati. Graphic: CincyStreetcar blog .

by John Schneider

An early turning point — there have been many of them — in the long-running effort to build the Cincinnati Streetcar occurred in one of the meetings that evaluated five potential routes. The early consensus favored a straight route on one-way parallel streets anchored by Cincinnati’s convention center, which has been expanded twice in the past thirty years.

Then something remarkable happened. The CEO of Cincinnati’s Convention and Visitors’ Bureau stood up and said, “Look, don’t build this for tourists — they are looking for things to do and they will find the streetcar wherever it is. Let’s build this for Cincinnatians.”

So an alternative quickly rose to the top — a diagonal alignment from southeast to northwest across the basin of downtown Cincinnati that puts just about every major destination within a couple of blocks of the line.

What proved to be key is the connection between employment and housing. While Cincinnati is a small city, it is home to a surprising number of large corporations, including Procter & Gamble, Macy’s, and the Kroger Company. There are seven Fortune 500 companies within a couple blocks of the streetcar line.

Most of these companies, their law and accounting firms and other support services are clustered a few blocks north of the Ohio River. Our region’s bus system is concentrated at the center of this agglomeration, and about 20% of downtown workers commute by bus. The streetcar line would end up flowing through the middle of this too.

At the other end of the line is Over-the-Rhine, so-named by German immigrants who compared the river they knew in their homeland to an early Cincinnati canal bordering OTR. Crossing the canal and going downtown was like “going over the Rhine.” And the name stuck.

Once home to perhaps 35,000 residents, OTR’s population dropped to around 5,000 or so in the 1990’s. Mostly vacant but blessed with beautifull (and mostly intact) Italianate townhouses, the neighborhood had been experiencing a slow comeback for several decades but was losing the battle to the elements and parking lots.

It was an obvious match: downtown workers are the best prospects to repopulate a neighborhood near lots of jobs but not really close enough to be walkable by everyone in all weather and at all times of the day. The streetcar solves that problem.

So the route will traverse the one-way couplet of Main and Walnut in the CBD, cross east/west at its midpoint to travel on another couplet, Elm and Race, which bracket Findlay Market, one of the oldest continuously operating public markets in the country. And perhaps the most authentic and diverse place in all of Cincinnati.

What else is along the Cincinnati Streetcar route? Plenty.

Fountain Square is the symbolic heart of our city and a focus of major investment. When the Reds win the World Series again, thousands of Cincinnatians will gather on the Square to celebrate. No one will require an invitation. It will just happen. The streetcar travels along the edge of the Square.

Speaking of the Reds, the Great American Ball Park is located near Stop #1 for the Cincinnati Streetcar. And Paul Brown Stadium, home of the Bengals, is four blocks away. These facilities are co-located in a huge Ohio River redevelopment project now known as The Banks, a billion dollars of new housing, restaurants, hotel and office space.

For 222 years, Cincinnati didn’t have a flood-proof riverfront, the Ohio River having a nasty habit of fluctuating wildly depending on upstream rainfall. As a result, not much could ever happen there. Now it will, because the parking for the teams — eventually to become one of the largest underground parking garages in North America — provides an invisible, floodable pllatform for the development above. The center of The Banks is about four blocks from Fountain Square with an uphill walk, so the streetcar will help bridge the distance and make commercial and hotel development there more promising.

There are other important destinations along the route of the Cincinnati Streetcar:

• Two-thirds of all the major cultural attractions in the Cincinnati region.
• Two new parks, one on the riverfront, the other in Over-the-Rhine.
• Cincinnati’s main library, now the busiest library building in the United States. There is also a historic private library on the line — one of its founders, a U.S. president.
• A new $72-million-dollar K-12 School for the Creative and Performing Arts, the first of its kind in the nation, which was originally established a half-mile away.
• Several new hotels and more in planning plus three large apartment buildings.
• Many bars and restaurants all along the line and more on the way. Cincinnati is getting to be a foodie town.

While the streetcar is mostly associated with Over-the-Rhine, economists estimate that the greatest real estate gains will occur in the north frame of the CBD. Over-the-Rhine is intimate and charming, and that’s why it is cherished by Cincinnatians. But most of the large parcels of land and buildings suitable for re-use as housing are in the “Empty Quarter” of the CBD between Fountain Square and OTR. Except for the Aronoff Center for the Arts, very little happens there nights and weekends. The streetcar will give this area new life.

City officials plan to extend the streetcar up the hill to Uptown area, to the University of Cincinnati with its 42,000 students and to the several hospitals near it. Downtown Cincinnati is the largest employment center in this 2.1-million-person region. Uptown Cincinnati is second.

A long-awaited sight: streetcar construction on Cincinnati's Elm Street. Photo: Travis Estell.

A long-awaited sight: streetcar construction on Cincinnati’s Elm Street. Photo: Travis Estell.

The key takeaway from Cincinnati is diversity of uses — connecting the two largest employment centers in the region with underpopulated historic districts between them, a large and growing public market, plus parks, schools, libraries, hotels and restaurants. When you put it all together, you have the likelihood of the streetcar’s near round-the-clock use almost every day of the week.

The Over-the-Rhine loop of the Cincinnati Streetcar will open for testing in mid-2015, the CBD loop about a year later.

Great things are happening in Cincinnati. Plan to visit soon.

Ed Tennyson: Streetcars use streets more efficiently


lrn_tor-lrt-stc-Rte504-dntn-bdg-pax-20120810-0255-x1_lhToronto streetcar downtown in August 2012. Photo: L. Henry

A recent Toronto poll found that opinions of metro-area respondents were almost evenly split on a plan to ban motor vehicles and allow only streetcars to operate on King Street (one of the downtown’s major thoroughfares) during morning peak hours, with 40% favoring the idea and 43% opposing it. While the plan had overwhelming support in the inner-city, the metro area’s more affluent, conservative suburbs (e.g., Scarborough) tended to oppose it. (Suburban voters have also tended to support conservative Mayor Rob Ford, who promotes policies similar to those of the USA’s Tea Party.)

The poll elicited the following observations and comments from Edson L. Tennyson, a renowned transportation engineer and consultant to the Light Rail Now Project. Ed is widely respected within the North American public transportation industry, having served as manager of several major transit agencies as well as Transportation Engineer for the City of Philadelphia and Deputy Director of Transportation for the State of Pennsylvania.

Without facts the people responding to that poll do not know what they are talking about. Since King Street is in the Old City, what business is it of Scarborough?

Let us look at the facts. A lane of autos waiting at traffic signals can move only 900 passengers per hour, not enough to keep a city busy or healthy. I do not know the streetcar headway, but with 56,700 weekday passengers, it sounds like 4,500 one-way in the peak hour, 5 times auto capacity. With 90 people per 4-axle car, that would require a 1.2-minute headway, 50 cars per hour. With articulated cars, a 1.8-minute headway could handle it.

The point is, who wants to allow 900 [Mayor Rob] Ford supporters to block the movement of 4,500 people per hour? Polls will not move anyone, but those 800 automobiles with 900 people will block 4,500. That is stupid, uneconomical, and grossly unproductive. When gridlock gets bad, transit speed falls to three (3) miles per hour. A streetcar costing $235 per hour will cost $78 per mile at three miles per hour; but at 6 miles per hour, which might be possible with no autos, the streetcar cost falls to $39 per mile, a saving of 50 percent for farepayers and taxpayers. If the media had the integrity and equity to explain it that way, I am sure the polls would change drastically in favor of streetcars.

[Misguided] politicians like Mayor Ford were running the U.S. Congress in 1959 when they banned streetcars from the District of Columbia [i.e., Washington, DC]. They did it to speed auto travel, but it did not work that way. It sped auto travel, all right — away from the city instead if into it.

Back then, Washington’s streetcars were almost as busy as Toronto’s streetcars. They made a profit to subsidize bus service, but they annoyed motorists. Traffic engineers wanted the streetcar lanes for auto left turns, a very low-volume use. Traffic engineers were trained at the Eno Foundation, then subsidized by General Motors. They were required to teach the need to eliminate streetcars.

The last [Washington] streetcar ran in 1962. Buying new buses escalated fares drastically and drove away most riders. Many downtown department stores went out of business. People with good jobs moved out of the city to escape auto congestion caused by automobiles, not streetcars.

From 1948 to 1975, transit use in Washington fell by 72%. The population fell from 750,000 to 590,000. By 1990 the City had so much debt it could not function. Congress had to bail it out, castrating City Council.

By then, MetroRail [rapid transit] was growing large enough to replace the streetcars and greatly reduce bus dependence. Transit increased almost 300% from 1975 to now. The Mayor just announced a tax cut as the city has too much money. The population is growing with higher-income people.

When MetroRail was planned they took a close look at Toronto to get it right. They did. [URT note: Washington, DC’s Department of Transportation has projects under way to re-introduce streetcar service to the city, thus supplementing the Metrorail rapid transit system.]

[This article has been slightly edited from the version first published on the Light Rail Now blog. Thanks to Light Rail Now for their kind permission to re-publish it.]

Cincinnati’s “Mr. Streetcar” makes case for Cincy project on radio


John Schneider photo

John Schneider [Photo: Cincinnati.com]

Cincinnati, Ohio — This city’s streetcar starter line project is under way … but so is the continuing fight against it by rail transit adversaries.

On Thursday, July 18th, local airwaves became a debate forum as John Schneider (co-principal of Urban Rail Today) sparred with 55KRC talk radio host Brian Thomas over the pros and cons of the city’s project, now surging forward with a fresh infusion of necessary funding (see Cincinnati signs streetcar construction contract). Here’s a brief description from the CincyStreetcar Blog:

John Schneider, aka Captain Transit aka Mr. Streetcar, was back on the radio this morning. He was invited to join Brian Thomas on his regular morning show on 55 KRC.

The two discussed the first phase of the Cincinnati Streetcar project in detail, and also discussed the merits of rail transportation in general.

The discussion started with Brian Thomas going on an uninterrupted prelude where he discussed the City of Cincinnati’s finances and its lack of ability to proceed with the project.

“The fundamental problem with Cincinnati, and the fundamental opportunity is we’ve lost population and we need to repopulate our city. We have a city that was built for 500,000 people, but we only have 300,000 people today,” Schneider explained to an agreeable Thomas. “But the snow still falls on Martin Luther King Boulevard and it has to be plowed, the grass still grows in Mt. Airy Forest and it has to be cut.”

Schneider went on to explain that investing in the Cincinnati Streetcar will help stabilize the city’s tax base and repopulate the city, in perhaps the greatest challenge and opportunity the Queen City has.

Perhaps not surprisingly, Thomas spent almost the entire interview using anecdotes and anti-city hysteria to support his points, but he did loudly profess how much of a bus fan he is.

CincyStreetcar Blog also provides its own link to a nice, compact recording of the full 55KRC program, lasting about a half-hour.

Yak jock Brian Thomas was not only adversarial, but also somewhat overbearing. After long orations of his own view, he’d ask John Schneider a question, then interrupt him about a couple of sentences into his response. In fact, it didn’t appear that John was ever able to complete a response without interruption. Neverless, John maintained a cool, professional demeanor and seems to have presented a good case for the Cincinnati project.

Much of the de facto on-air debate focused on Thomas’s claims that buses could do the job at less cost (the “Just like rail, but cheaper” argument). But (before being interrupted each time) Schneider managed to emphasize some of the major advantages of rail transit.

It’s almost a sure bet that rail transit opponents actually ride public transit extremely rarely, if ever — and, especially before an audience similarly unfamiliar with the actual differences, this sophistic anti-rail rationale can effectively hoodwink some observers. But the reality is that a streetcar is far more attractive to the public than a bus, even for what will be, in the Cincy CBD, short circulator trips. There’s more personal space, you can board/deboard much faster, the stops are far nicer, the trip is faster.

As a result, significantly higher ridership is attracted. And, in most cases, in turn, rail’s operating and maintenance cost per passenger-mile is lower than for similar bus service.

One of the more curious aspects of the debate was Thomas’s argument on the claimed drawbacks of rail’s route permanence, and his praise for the supposed superiority of being able to “flexibly” change a bus route at will. Despite Thomas’s professed devotion to bus transit, almost any seasoned regular bus rider might seriously wonder whether he really rides the bus as often as he claims. As most regular riders know all too well, “flexible” route diversions are one of the greatest banes of bus passengers, especially when these diversions occur frequently because of special events such as parades, marathons, street fairs, and similar activities.

What this “flexibility” means for many a regular commuter, for example, is that you walk vigorously to your usual bus stop for your after-work trip home, only to find it closed because your bus has been re-routed six to eight blocks away — and you can’t possibly make your bus on time. (But it’s probably delayed by all the street activity and re-routings, anyway.)

In short, while route “flexibility” might be very handy for the transit agency (and muncipal public works roadway department) … it’s hell for the passengers. The people of Cincinnati — and, indeed, any community considering rail vs. bus alternatives — need to ask themselves if this is the outcome they really want.

Cincinnati signs streetcar construction contract


streetcar

Cincinnati’s modern 100% lowfloor streetcars will be constructed in Elmira, NY by CAF USA.

Cincinnati, Ohio — After many months of civic agonizing and political wrangling over a budgetary shortfall, this city’s streetcar project is back on track with the signing on July 15th of the major contract for trackage and other infrastructure with the consortium of Messer Construction, Prus Construction, and Delta Railroad.

urt_cin-lrt-stc-contract2-20130715

The $71.4 million contract has been facilitated by the City Council’s recent approval of $17.4 million in additional capital funding to cover the unanticipated shortfall, and includes an extra $492,933 for increases in material expenses, labor and equipment, cold weather protection, and bonding costs. With the purchase of rolling stock and other expenses, total capital investment cost of the project is now estimated at about $133 million. That’s about $37 million a mile for the 3.6-mile single-track-loop route.

Under the revised construction schedule, all work will be completed by March 2016 and passenger service is projected to begin in September 2016.

Read more:

Construction Contract Signed

Cincinnati Streetcar Scheduled to Open Sept. 15, 2016

New light rail projects in study beat BRT


Phoenix light rail transit (LRT, left); Los Angeles Orange Line "bus rapid transit" (BRT, right). Photos: L. Henry.

Phoenix light rail transit (LRT, left); Los Angeles Orange Line “bus rapid transit” (BRT, right). Photos: L. Henry.

by Lyndon Henry

New light rail transit (LRT) projects came out ahead of new bus rapid transit (BRT) projects that were included in a research study I presented last November (2012) to the 12th National Light Rail Transit Conference in Salt Lake City, sponsored by the Transportation Research Board (TRB) and American Public Transportation Association (APTA). Dave Dobbs, a longtime colleague, helped me conduct the study.

In part, this research was a response to the assertions of critics of rail transit who maintain a constant barrage of attacks on rail, trying to convince the public at large and decisionmakers that public transit (especially rail) is just a waste of money … and that, if you must install something fancy, so-called “BRT” is invariably cheaper and better (or “Just like light rail, but cheaper…”). However, these attacks rarely appear in independent professional forums like this one, co-sponsored by the TRB (an affiliate of the National Academy of Sciences).

All papers accepted by the TRB for publication/presentation — including this work, titled Comparative examination of New Start light rail transit, light railway, and bus rapid transit services opened from 2000 — must undergo a rigorous peer-review process critically examining their methodology and conclusions.

My PowerPoint presentation to the conference has been placed online by the TRB and can be found here:

http://onlinepubs.trb.org/onlinepubs/conferences/2012/LRT/LHenry.pdf

In addition, I discussed the study — both the methodology and the results — in several articles published in my online blog column at Railway Age:

Research study: New LRT projects beat BRT [26 November 2012]

Research: BRT can truly be pricier than LRT [14 January 2013]

Study: LRT ridership gains are spectacular [18 February 2013]

Here are some summary results, excerpted from the Railway Age articles:

How well did LRT and BRT final costs compare with budget estimates? LRT again did better, exceeding budget by only 2% on average, while BRT averaged 35% above budget.

In terms of capital cost, for “substantial” installations (5% or more of route length involving heavy civil works), LRT was a clear winner, with an average cost per mile of $80 million, less than a fifth of BRT’s average of nearly $452 million. (All costs in 2012 dollars.)

Where electric LRT really excelled was in achieving ridership goals. On average, LRT projects seemed to meet their ridership targets at about twice the rate of the BRT projects, using the “ridership achievement index” we developed for the study (which accounted for the pace at which projected ridership was being achieved).

It should be noted that some BRT projects didn’t do so badly — Cleveland’s “HealthLine” project (Euclid Avenue) was achieving its target at a 60% faster pace than expected, while Los Angeles’s Orange Line busway was reaching its ridership at nearly 3 times the projected rate.

But some of the LRT results were really spectacular. St. Louis’s St. Clair Extension of Metrolink, for example, was racing towards its ridership goals at over 7 times the predicted rate; Minneapolis’s Hiawatha line at six times; and Denver’s Southwest LRT at more than 6 times. (It should be noted that 3 out of the 20 LRT projects studied were failing to meet projected growth rate targets; nevertheless, the overall LRT average still exceeded BRT’s.

There’s a lot more, both in the PowerPoint presentation, and in the full Railway Age articles.

Providence streetcar plan hinges on federal funding


urt_prv-lrt-stc-sim-dntn-night-crowds-x1_City-of-Prv
Simulation of Providence streetcars serving downtown crowds at night. Source: City of Providence.

Providence, Rhode Island — This mid-sized New England city is ready to install a new streetcar system. All it needs is some federal cash.

According to a recent report from WPRI-TV News in Rhode Island’s capital city, local and federal officials are asking the federal government for $39 million to help pay for about a third of the cost of constructing a new streetcar line to connect the Upper South Providence neighborhood near Rhode Island Hospital to College Hill on the downtown’s East Side.

The following infographic provides a map and further information:

urt_prv-lrt-stc-map-infographic-20130610_City-of-Prv
(Click to enlarge) Source: City of Providence.

The 2.1-mile, $114.4-million starter line would have 11 station-stops and 4 streetcars. The federal money would come from the Transportation Investment Generating Economic Recovery (TIGER) grant program, a component of the Obama administration’s original 2009 economic stimulus package.

As the news report explains,

The rest of the project would be paid for with an array of city and state bonds as well about $5.25 million in additional federal funds secured by the Rhode Island Public Transit Authority. Sponsorships, advertising revenues and $2 fares would be used to sustain the system once it got up and running.

Once the project gets a green light, construction would begin by late 2015 and streetcar service would open to the public in 2017.

Read more here

Alstom takes the leap into North American light rail market


otw-lrt-sim-Alstom-Citadis-Spirit-x1_Alstom
Alstom’s Citadis Spirit for Ottawa. Simulation: Alstom

Philadelphia — With an opulent reception and major flourish, on the evening of June 3rd during the annual Rail Conference of the American Public Transportation Association (APTA), the third of the “Big Three” global rail transit car producers announced its entry into the North American light rail transit (LRT) rolling stock market.

Unveiling its car model called the Citadis Spirit, Alstom company executives emphasized that “the Citadis Spirit builds upon the experience of more than 1,700 Citadis light rail vehicles in service worldwide…” and noted that “with over 30 cities in the U.S. and Canada planning new light rail or streetcar systems, the vehicle includes unique features to satisfy the transit needs and support the economic development goals of North American cities.”

Alstom’s move is not only a major step for Alstom, and for the North American LRT car market, but also a de facto testament to the vigorous growth — and strong potential growth — of LRT across North America. The two other “Big Three” producers — Siemens and Bombardier — have been major supplliers for the transit railcar market, [articularly in the USA and Canada, and a number of other firms, both foreign and domestic (e.g., Kinkisharyo, Breda, Kawasaki, Rotem, Skoda, Inekon, Brookville Equipment Corporation, Oregon Iron Works), have also been important players in the industry.

Alstom’s June 3rd press release touted important features and advantages of the Citadis Spirit car:

Those features include a 100% low floor design and the ability to operate at speeds of up to 65 mph. Hence, the Citadis Spirit is versatile and can provide both a streetcar service in mixed traffic as well as a commuter service on dedicated infrastructure. Its low-floor boarding and interior, which is free of steps, provides better accessibility as well as a safer and more comfortable ride to users of all walks and ages. The vehicle also is totally modular in length and can be expanded as a city’s transportation needs grow over time. Additionally, the Citadis Spirit can be paired with one of Alstom’s proven off-wire power supply systems to preserve historic cityscapes and minimize impacts on the environment.

Alstom has already secured a major contract for the Citadis Spirit. In February, the company announced its first order — from the City of Ottawa for its new LRT system — with a contract to deliver 34 cars, plus an option for an additional 21 cars, and 30 years of maintenance services. The car for Ottawa will be a high-capacity version of the Spirit with a total length of 160 feet.

As of 2015, says Alstom, the Citadis Spirit will be manufactured in North America . Its design and manufacturing process are very modular and flexible, allowing final assembly to be localized close to end-users and municipalities.

In a statement, Alstom Transportation’s President, Guillaume Mehlman, underscored that

in developing the Citadis Spirit, we recognized that every city has a unique ambition for public transportation and an expectation that our mobility solutions boost sustainable economic development. With this vehicle’s versatility and modularity, Alstom is able to respond to those expectations as they evolve over time. Our Design & Styling department can also customize the train’s interior and exterior design to embody each city’s unique character. Each new Citadis Spirit will be shaped by and a reflection of the community it serves.

Alstom-Citadis-Spirit-diagram-modular-expansion_Alstom
Graphic illustrates how Citadis Spirit’s capacity can be expanded by adding modules to the basic car. Graphic: Alstom

Alstom’s brochure on the Citadis Spirit provides this technical information:

Alstom-Citadis-Spirit-chart-dimensions_Alstom

Alstom-Citadis-Spirit-chart-interior_Alstom

Alstom-Citadis-Spirit-chart-technical_Alstom

Alstom-Citadis-Spirit-chart-main-equipmt_Alstom

Alstom-Citadis-Spirit-chart-options_Alstom

[This article was first published on the Light Rail Now blog. Thanks to Light Rail Now for their kind permission to re-publish it.]

Milwaukee aiming to start streetcar line construction in 2014


urt_mil-lrt-stc-sim_urbanmilwaukee-dot-com

Milwaukee streetcar simulation: UrbanMilwaukee.com

 

Milwaukee, Wisconsin — After well over a decade of controversy and political gridlock, engineering design is now under way, and squabbling has even started over who must pay for moving utilities.

Planners and city officials are aiming to start construction in 2014, with tentative completion and opening of the line targeted for 2016. The initial 2.1-mile starter line is projected to have an investment cost of $64.6 million. That’s about $31 million per mile — but the cars and maintenance shop (carbarn) are included. (For comparative purposes, when freeways and similar large road projects are discussed, the costs of motor vehicles and all their garages and maintenance facilities are never included in project estimates.)

The Federal Transit Administration has committed funding of $54 million to the project.

The route extends from 4th St. on the southwest, eastward along St. Paul, northward along the Van Buren corridor, then westward on Ogden to its northeastern terminus.

urt_mil-lrt-stc-map-proposed-rte-x1_Walkers-Point-Blog

Map: Walker’s Point Blog

 

Consulting firms HNTB and HDR have been hired to perform final engineering work.

For more details, check out this recent article in the Milwaukee Business Journal: Milwaukee hires engineer to continue streetcar design work.